One Partner. Cost Efficient. Smarter Charger Solutions.
Since 2019, we have installed over 1,000 EV chargers, featuring trusted brands like HiCi, Hiconics, and ABB, for heavy logistics operators and large-scale commercial structures. We deliver turnkey EV charging solutions, providing full Engineering, Procurement, & Construction (EPC) without the hassle of managing multiple contractors.
Our In-House Team Manages the Complete Lifecycle:

#1
Site Survey & Visual Drawings
Precision planning and spatial design tailored to your specific location.

#2
Grid Supply Liaison & Document Submission
We handle the red tape, managing all utility coordination and regulatory approvals.

#3
Professional Installation & Site Supervision
Expert, safe execution overseen by our dedicated site managers.

#4
Commissioning of Charger
Rigorous system testing to ensure peak operational performance before hand-over.

#5
Charger Registration
Complete management of all required system onboarding and compliance.

#6
After-Sales Support
Proactive maintenance and responsive care to guarantee your chargers stay online.
Our Portfolio
Discover our latest projects
Testimonials
“EVOne’s commitment to providing top-quality charging infrastructure has been key to our sustainability efforts at StorHub. Their seamless installation process and attention to detail made it easy to integrate EV chargers across our sites. Our customers and employees have greatly benefited from having reliable, green charging options, and EVOne’s support has been exceptional throughout the project.”
Ms. Geoffrey, GM of Sustainability, StorHub
“Partnering with EVOone has empowered us to accelerate our clean energy transition with reliable EV charging solutions. Their ability to design and implement scalable systems has been invaluable in supporting our operations across multiple sites. The EVOone team’s responsiveness and technical expertise ensure smooth deployments, while their commitment to sustainability aligns perfectly with our long-term vision. We look forward to deepening this partnership as we continue to expand our EV initiatives.”
Mr. Lee, Director of Operations, Cnergy
“Partnering with EVOone has been a game-changer for our electric vehicle fleet. Their network of charging stations is extensive, and the green energy initiative aligns with our sustainability goals. The collaboration has significantly improved our operational efficiency, and we appreciate their dedication to innovation and customer service. We look forward to continuing this journey together.”
Mr. Ang, General Manager, Strides Premier Taxi
“EVOone has been instrumental in helping us transition our fleet to electric vehicles. Their reliable charging stations and exceptional customer support have made the process smooth and efficient. The ability to monitor and manage our charging operations through their platform has also improved our operational efficiency. EVOone’s focus on green energy aligns perfectly with our vision for a sustainable future. We couldn’t have asked for a better partner.”
Mr. Lim, Operations Manager, Business Integrator
“Working with EVOone has been an outstanding experience. Their ability to deliver large-scale EV charging solutions for our depots has greatly contributed to our sustainability targets. The team’s professionalism and technical expertise ensured a smooth and timely installation, and their commitment to green energy resonates with our environmental goals. We are excited to continue expanding this partnership as we grow our EV fleet.”
Mr. Tan, Sustainability Manager, PSA Singapore

Frequently Asked Questions (FAQ)
Before installation, there are a few important requirements:
✔️ Site survey to assess feasibility
✔️ Available electrical power capacity at your premises
✔️ Sufficient installation space and cable routing
✔️ Main switchboard (MSB) suitability
✔️ Landlord/building owner approval (if applicable)
✔️ Type of vehicles to be charged (cars, vans, buses, trucks)Our team will conduct a full site assessment and advise on the most cost-efficient setup before any installation begins.
Yes — if you are purchasing electric heavy vehicles in Singapore, you may qualify for the Electric Heavy Vehicle Charger Grant (EHVCG) under Land Transport Authority.
The grant offers:
✅ Up to 50% co-funding
✅ Capped at $30,000 per charger
✅ Up to 3 chargers per site
Requirements include:
• A confirmed EV purchase order (PO) or deposit receipt
• Charger must be minimum 50kW DC
• Charger must be installed at your business premises
• Must serve heavy vehicle lots
Grant period: 1 Jan 2026 to 31 Dec 2028.
Our installation process is simple and structured:
Step 1: Initial consultation
Step 2: Site survey & power assessment
Step 3: Proposal & quotation
Step 4: Grant advisory (if applicable)
Step 5: Electrical design & authority submissions
Step 6: Installation by certified team
Step 7: Testing & commissioning
Step 8: LTA registration
Step 9: Handover & training
This ensures your charger is compliant, safe, and operational.
We supply and install a full range of DC fast chargers depending on your operational needs:
30kW – Light commercial / fleet
60kW – Fast daily charging
120kW – High-utilization fleets
180kW – Multi-vehicle charging
240kW+ – Heavy-duty / bus depots / logistics hubs
The right charger depends on:
Vehicle battery size
Daily mileage
Downtime availability
Existing power supply
Our engineers will recommend the optimal size.
Yes. In Singapore, all EV chargers must be registered with Land Transport Authority before they can be used.
This includes:
Charger must be LTA type-approved
Installation must be certified fit for use
Registration mark must be affixed after approval
We can manage the full registration process on your behalf for a hassle-free deployment.
DC chargers require significantly more power than AC chargers.
General guide:
30kW charger → approx. 50A
60kW charger → approx. 100A
120kW charger → approx. 200A
180kW charger → approx. 300A
Your existing incoming supply, transformer capacity, and spare load will determine what can be installed.
If power is insufficient, upgrading may be required.
Typical timelines:
Site survey: 1–3 days
Quotation & engineering review: 3–7 days
LTA grant submission: 2–3 weeks
Installation: 1-2 weeks
Testing & commissioning: 1 day
For projects requiring power upgrades or authority approvals, timelines may vary.
Early planning helps speed up deployment.